JOB 01-
Finish-
Contract-
Crash $-
Net $-
Network · AON
Critical (TF 0)
Near-critical (TF 1-2)
Float
Time-scaled bar chartdays
Showing the optimal plan. Reset to try again (stars aren't awarded after a peek).
Tap an activity
-
How to play
Each job is a CPM network. Every box is an activity; arrows are finish-to-start logic. The project finishes when the longest path finishes, and that path is critical.
- Tap an activity, then − to crash it a day (overtime, extra crew) at its cost per day, down to its crash limit. + gives a day back.
- Crashing an activity with float buys nothing. Watch the near-critical paths: as you crash, they go critical, and then every critical path has to be shortened together.
- Hard-date jobs: finish by the contract day at the lowest crash cost. Late is rejected.
- LD jobs (red tag): net cost = crash + liquidated damages − early bonus − overhead saved. Sometimes paying LDs is the cheap answer.
- Hit Issue to submit the recovery schedule. It's checked against the true optimum: ★★★ optimal, ★★ within 10%, ★ within 25% (LD jobs: of the savings available). One star clears a job. Jobs run in order, but you can open any of them.
Shortcuts on a keyboard: arrows pick activities, −/+ crash and restore, U undo, Enter issues.